Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Unable to change baseline

3 replies [Last post]
Rangarajan Ramaswamy
User offline. Last seen 2 years 3 days ago. Offline
Joined: 1 Dec 2009
Posts: 24
i have created & assigned my baseline to my project,but now i want to change it . and i am unable to.

Also whenever i press F9 to schedule my project some of the activities automatically shifts to the current data date.
PLZ help

Replies

Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

You are welcome.

Izam Zakaria
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Pal,

It’s working man

Thx
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Raj,

1. Go to Project --> Assign Baselines, Change your Project Baseline or Primary to "Current Project". When done, again, go to Project --> Maintain Baselines, highlight the baseline then select restore. Now you can change and assign a new baseline.

2. Check the predecessors/successors of these activities. I guess, it is an open-ended activities.

Regards,

Arnold