Unable to change baseline

3 replies [Last post]
Rangarajan Ramaswamy
User offline. Last seen 2 years 9 weeks ago. Offline
Joined: 1 Dec 2009
Posts: 24
i have created & assigned my baseline to my project,but now i want to change it . and i am unable to.

Also whenever i press F9 to schedule my project some of the activities automatically shifts to the current data date.
PLZ help

Replies

Arnold Puy
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

You are welcome.

Izam Zakaria
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Pal,

It’s working man

Thx
Arnold Puy
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Raj,

1. Go to Project --> Assign Baselines, Change your Project Baseline or Primary to "Current Project". When done, again, go to Project --> Maintain Baselines, highlight the baseline then select restore. Now you can change and assign a new baseline.

2. Check the predecessors/successors of these activities. I guess, it is an open-ended activities.

Regards,

Arnold