1. Go to Project --> Assign Baselines, Change your Project Baseline or Primary to "Current Project". When done, again, go to Project --> Maintain Baselines, highlight the baseline then select restore. Now you can change and assign a new baseline.
2. Check the predecessors/successors of these activities. I guess, it is an open-ended activities.
Member for
18 years 6 monthsRE: Unable to change baseline
You are welcome.
Member for
19 years 5 monthsRE: Unable to change baseline
Pal,
Its working man
Thx
Member for
18 years 6 monthsRE: Unable to change baseline
Hi Raj,
1. Go to Project --> Assign Baselines, Change your Project Baseline or Primary to "Current Project". When done, again, go to Project --> Maintain Baselines, highlight the baseline then select restore. Now you can change and assign a new baseline.
2. Check the predecessors/successors of these activities. I guess, it is an open-ended activities.
Regards,
Arnold