Hi Raj,



1. Go to Project --> Assign Baselines, Change your Project Baseline or Primary to "Current Project". When done, again, go to Project --> Maintain Baselines, highlight the baseline then select restore. Now you can change and assign a new baseline.



2. Check the predecessors/successors of these activities. I guess, it is an open-ended activities.



Regards,



Arnold