Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global change not working for baseline programme

2 replies [Last post]
Kevin Rayner
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 9 Jan 2009
Posts: 17
Groups: None

I am aware of the need to change the planned start and planned finish of a baseline programme before attaching it to the programme that I am usuing to demonstrate a delay.

However in certain instances the planned dates are not being changed. ie an activity in progress with and actual start of the 30 May 2018 and a finish of the 3 Dec 2018 after running the global change to set the planned dates gives a planned start of the 30 May 2018 but a finish of the 30 Nov 2018 and not the 3 Dec 2018.

I assume that the global change is:

Condition 1 activity complete. planned start=actual start planned finish=actual finish

Condtion 2 activity in progress. planned start=actual start planned finish=finish

Is this correct?

Replies

Kevin Rayner
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 9 Jan 2009
Posts: 17
Groups: None

You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?

Zoltan Palffy
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

how come you are mixing planned start date with finish dates  ?

actual start = planned start

actual finish = planned finish