Question about late dates

1 reply [Last post]
Brian Yung
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 11 Mar 2009
Posts: 26
Good day Gentlemen,

I would like to know why P6 show late dates eventhough the activity is comlete. From memory, in P3 whenever an activity is completes, the late start/finish date would either be empty or show the actual dates.

Is this normal?

Regards,

Brian

Replies

Dieter Wambach
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Brian

Yes, it’s by design. If an activity has an actual finish, the algorithm doesn’t touch it and leaves the late finish. You can use it to compare with original planning. The field "Finish" turns from early to actual finish.

Regards
Dieter