Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Question about leveling resources and durations

1 reply [Last post]
Scott Parker
User offline. Last seen 12 years 1 week ago. Offline
Joined: 26 Jul 2012
Posts: 6
Groups: None

I was wondering how to set my activities so that when I schedule and level my resources my durations change automatically?  I have been given the folowing information

 

Budgeted Hours for the activites

Available Manpower

Start date

Finish date

Set Calendar

 

I want to be able to play with my manpower and calendar to effect durations.  Hope this makes sence to someone.

 

Scott

Replies

SM PUM
User offline. Last seen 10 years 39 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

In resource levelling Option "CHeck Off" Preserve schedule Early & Late Dates.

regards