question about data date

2 replies [Last post]
Alaa Al haj
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

hi

we are updaing the program on weekly basis - our cut off date is thursday

shall i use data date ( friday) in primavera 6 or thursday ?

 

thanks

Alaa

Replies

Ameen Pasha
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 21

Absulately Correct.

Ronald Winter
User offline. Last seen 4 years 3 days ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

The definition of a data date is the first available hour for new work to commence or existing work to continue.  If your status is current as of Thursday at 16:00, then a data date of Friday at 08:00 might be appropriate.  Good luck!