Late Start and Late Finish date issue while importing

3 replies [Last post]
Gowhar Mir
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 7 May 2018
Posts: 29
Groups: None

Hi there!

I am currently facing this issue wherein when I import a program into another computer the late start and late finish dates change. So technically my entire float is changing.

Any reasons why it might be so? 

I checked the calendar. It is same for both the projects.

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

just as I suspected glad that I could help 

Gowhar Mir
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 7 May 2018
Posts: 29
Groups: None

Thanks, Zoltan. I checked the calendars and there laid the problem, holidays weren't assigned in default calendar of one computer. 

Zoltan Palffy
User offline. Last seen 25 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

1 check the calendar again if it is using the default calendar then default calendar on your computer and the compueter where it came from may be different.

2 Also check the calendar at the bottom where it says to Inherit holidays and exceptions from Global Calendar that the correct one is choosen.

3. make sure that the data date DATE and TIME are the same

4. in the calculations options make sure they are using the same way when calculating successor relationships