Good day Gentlemen,
I would like to know why P6 show late dates eventhough the activity is comlete. From memory, in P3 whenever an activity is completes, the late start/finish date would either be empty or show the actual dates.
Is this normal?
Regards,
Brian
I would like to know why P6 show late dates eventhough the activity is comlete. From memory, in P3 whenever an activity is completes, the late start/finish date would either be empty or show the actual dates.
Is this normal?
Regards,
Brian