Importing files from p3 to p3e

2 replies [Last post]
Stanley Obeleagu
User offline. Last seen 14 years 50 weeks ago. Offline
Joined: 6 Feb 2009
Posts: 6
I recently imported a work program from p3 to p3e and

noticed that some key dates(M.C.,Ready for

commissioning,Demobilisation) changed when i rescheduled

the P.O.W.(Programme Of Work) What could be the problem?

Replies

Stanley Obeleagu
User offline. Last seen 14 years 50 weeks ago. Offline
Joined: 6 Feb 2009
Posts: 6
Thank you Dieter,

I will check it out.

Regards,

Stanley.
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Stanley

On your documentation cd there is a directory From P3 to P6: Before you’ll start the import read this chapter: "Converting P3 Projects to P6" (starts page 115) to understand the differences.
In your case I assume most probably reasons are the calendars or the scheduling options (lags?).

Good luck
Dieter