Project must finish by

3 replies [Last post]
Hatem Hussen
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 4 Mar 2008
Posts: 20
Some of my projects when i convert them from P3 to P5 and the project finish date for example is 1/4/2009 and the Project must finish by is 1/4/2009 the total float is coming -1 day
can any body help pls

Replies

Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Hatem,

I addition to what Ronald said, check your user prefences -> Dates -> Time, check the box next to 12 hour. Check your project must finish date against with your Activity finish date. try to change the 12:00AM to 5:00PM

Try to compare these two things, thy must be equal in date and in time.


Regards,

Arnold
Hatem Hussen
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 4 Mar 2008
Posts: 20
thanks Ronald
Ronald Winter
User offline. Last seen 3 years 29 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
P5 works in hours & minutes but you have elected to view the results in days. This means that it has to round -0.5 days of float up to read “-1.” Change your user preferences to view hours and minutes and to see your durations with decimal fractions and you will probably see the cause of your odd reading. Good luck!