Bearing Negative Total Float if Apply Must Finish date

3 replies [Last post]
Cecil Soliva
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20
Hi Planners:

I made a project having an early finish date of October 15, 2010 and the same I provided to the project details must be finished on October 15, 2010. I found out that the Total Float of the critical Path changes from 0 to -1. How does P6 reads with this regards?


Thank you,

Cecil

Replies

Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

You are welcome.

Cecil Soliva
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20

Thanks again Arnold..I’ve wasted a lot of time, thinking how it became -1 TF..


regards,

Cecil

Arnold Puy
User offline. Last seen 9 years 47 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cecil,

Try to check the finish date.

1. Go to Edit --> User Preferences --> Dates tab, Time, tick Show minutes and select the 12 hour (1:30 PM).
2. Go to Enterprise --> Projects
2. In Projects Detail Tab --> Dates
3. In "Must Finish Date" if you notice the the time is 12:00 AM, change this to 4:00PM or 5:00PM. It depends on the calendar and time you use.

Otherwise, check your finish date. It should be the same with "Must Finish Date especially the time.

Regards,

Arnold