Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Productivity factor in P5

3 replies [Last post]
Yusuke Kamui
User offline. Last seen 14 years 48 weeks ago. Offline
Joined: 18 May 2008
Posts: 56
Groups: None
Hi,
Does anyone know how to factor the productivity efficiency in Primavera (P5)?
Currently I have an overall budgeted units for project amounting to 100,000 hrs. Considering an efficiency of only 85% so I need to add 15% on top of the budgeted units to equal to 100,000 + 15% = 115,000 hrs. So how to distribute or change each and every task in my schedule to equate the budgeted units total to 115,000 hrs?? Do I need to add 15% in every task’s budgeted hours?? Take note there are some task having actuals already. All of the task is a resource dependent, fixed unit type.

Thanks!

Replies

shiv rao
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 10 Mar 2008
Posts: 62
You need to use Global Chaneg .

And select Activity Resource Assignment .

Change Budgeted units for All REsources from 1 to 1.15

regards

shiv
Larry Rino
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 25 Oct 2007
Posts: 64
Sorry but you need to input the new figures (+15%) manually...

Good day
You can try increasing resource max units/time to 115% and recalculate.