Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Schedule % Complete

1 reply [Last post]
Richard Bowie
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 13
Groups: None
all activitys show 100% in the schedule % complete column but at summary lavel it shows 0%. the planned value labour units and budgeted labour units are the same value.

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Richard,

Check your resource if Price/Unit = 0 and your Budget Cost = 0. Work Around is to create a WBS Summary Activity for each WBS level and it will show the Schedule % complete total for each Summary.

HTH,
Rodel