Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

BL Budget At Completion and PV is Not Matching At Completion Total Cost for a Completed Activity

1 reply [Last post]
Ali Aljaberi
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 25 Apr 2019
Posts: 2
Groups: None

Hi,

6697
capture.jpg

I have an activity in my schedule that has a Budget At Completion=PV=EV=$16,451.87, while my At Completion Total Cost for that activity= $66,084.98 (as in the attached screenshot).

The Baseline was snapped two months after the activity finish date was actualized; I tried to update the BL couple of times for that specific activity, but its still showing No matching values. 

Anyone went through this situation before please?

Thanks.

 

Ali

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

release the baseline fix it then re-attach it.