Performance % Complete

8 replies [Last post]
niles luo
User offline. Last seen 13 years 20 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None
Dear all:
Can anybody give me some suggestion about how to calculate the value of ’Performance % Complet’ for an activity or a project in P3ec. Thanks a lot

Replies

Alex Wong
User offline. Last seen 11 years 27 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Hi

If you using Performance % Complete as well as Steps
your % complete will base on your step completion

If you only using performance % comp then it is a value entre by you of your estimated completion of the activity

HTH

Alex
Dinesh Kumar Dama...
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi Niles Luo,

Performance % complete is the earned value of any activity.Earned value can be based on quantities, cost mhrs etc.

In P3e if you are using performance % complete, it is better to base on the cost in updating the activity % percentage complete as P3e only uses cost in summarising the percentage at different WBS or activity code level.

I hope it clarifies.

Cheers.

Dinesh
Frank Neal
User offline. Last seen 1 year 34 weeks ago. Offline
Joined: 3 Feb 2003
Posts: 44
Groups: None
SPI = BCWP/BCWS.....not ACWS..this does not exist!
raed hussein
User offline. Last seen 11 years 14 weeks ago. Offline
Joined: 29 May 2007
Posts: 17
Groups: None
I would like to correct the following

Schedule Variance = BCWP-BCWS
Cost Variance = BCWP-ACWP
Schedule Performance Index (SPI) = (BCWP/ACWS)
CostPerformance Index (CPI) = (BCWP/ACWP)
raed hussein
User offline. Last seen 11 years 14 weeks ago. Offline
Joined: 29 May 2007
Posts: 17
Groups: None
display the WBS Window and click the earned value tab

choose the technique for computing the performance % complete

which is consider to calculate earned value

earned value = budget at completion * performance % complete
Steven Oliver
User offline. Last seen 11 years 45 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Which, whilst correct, doesnt address the original question.
Manoj Singh
User offline. Last seen 17 years 33 weeks ago. Offline
Joined: 17 Jan 2007
Posts: 2
Earned Value Measurement System (EVMS) is a rational method for Measuring Performance that can help the Project Teams manage their work more effectively by:-

1)Anticipating problems before they become acute
2)Using factual data to understand what is happening
3)Recognizing trends and correcting them
4)Applying lessons learned to improve future performance
5)Preventing Margin Slippage.


Here Are The Earned Value Terminology:-

BCWS = Budgeted Cost of Work Scheduled=Planned Value
BCWP = Budgeted Cost of Work Performed=Earned Value
ACWP = Actual Cost of Work Performed= Time Charged
Schedule Variance = BCWP-BCWP
Cost Variance = BCWP-ACWP
Schedule Performance Index (PI) = (BCWP/ACWP)
CostPerformance Index (SI) = (BCWP/BCWS)

Hope i am clear.
Steven Oliver
User offline. Last seen 11 years 45 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Define your interpretation of "Performance"