Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activities when imported moves out of WBS

2 replies [Last post]
Salman Ahmed
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Hi all,

Request your suggestions on the following situation:

I exported the activities for weightage calculations.When these activites are imported back to P6, they moved from their original WBS to Project level WBS.





Replies

Salman Ahmed
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 2 Mar 2010
Posts: 54
Thank you Mr.Rodel for your support.

Salman
Rodel Marasigan
User offline. Last seen 7 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Salman,

When exporting files from Primavera, don’t delete the WBS Code column, this is one of the basic unique identifier of activity. If this column remove and import back, all activities will move to Project level WBS and delete the current assignment.