TARGET

2 replies [Last post]
Lo Gary
User offline. Last seen 1 year 44 weeks ago. Offline
Joined: 7 Feb 2010
Posts: 49
Groups: None
Dear,

In P3, only 2 targets could be set. However, it is very often the programme would be revised 6 to 7 times or even more in a project of 2 to 3 years span. How could I set more targets while the old ones to be kept rather than delete the old versions.


GARY

Replies

Shah. HB
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

As Rafael rightly pointed out ,P3 is limited to 2 targets .It does not matter how many times you revise the baseline.Targets is for comparison purpose .
Rafael Davila
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230
Gary,

The targets or baseline are stored in separate files so there is no limit as to the amount you can have other than the limited characters for job names. Say about 36^4 = 1,679,616 (minus one, the actual job) if using all characters and numbers in your keyboard.

You can edit and work with your baselines as you wish. The two jobs limitation is for displaying the data in your layouts and graphic reports.