Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Unable to edit Baseline

4 replies [Last post]
Rangarajan Ramaswamy
User offline. Last seen 2 years 9 weeks ago. Offline
Joined: 1 Dec 2009
Posts: 24
i have created & assigned my baseline to my project,but now i want to change it . and i am unable to.

Also whenever i press F9 to schedule my project some of the activities automatically shifts to the current data date.
PLZ help

Replies

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline
Moved to P3 forum.

Raj: The software is supposed to move any activities that have not yet started to the data date when you press F9. The theory is, if it hasn’t started yet, it shouldn’t be showing in the past.
To tell the software an activity has started, check the ’actual’ box when you enter the start date.

If you want to change the baseline mid project, open up the target project whilst you do not have your live project open, you should be able to make the changes as normal.
shaik yakub
User offline. Last seen 8 years 39 weeks ago. Offline
Joined: 25 Jul 2007
Posts: 12
Is that possible for you to send a PRX on my Email id - yakub_sky@yahoo.co.in i vl have a look at that and let u know?

Shaik
Rangarajan Ramaswamy
User offline. Last seen 2 years 9 weeks ago. Offline
Joined: 1 Dec 2009
Posts: 24
thanx a lot yakub, i know that , but what if i have to change the baseline in the middle of the project.and also i have checked the activities but i dont know the first activity of every new project m creating automatically sets to the current start date and even if i change it to some back date , after pressing F9 it automatically shifts to the current schedule data in the F9 option
shaik yakub
User offline. Last seen 8 years 39 weeks ago. Offline
Joined: 25 Jul 2007
Posts: 12
Raj,
You can edit the Target dates only in the Baseline Programme But not in the Updated Schedule where u have assigmned target. Regarding the dates check the links of the activities.


Shaik