Actual earned quantity!! Not match with real situation!

2 replies [Last post]
Santhosh kumar Na...
User offline. Last seen 7 years 1 week ago. Offline
Joined: 7 Aug 2006
Posts: 66
Hi,
Iam facing a problem. In my program i loaded concrete qty with resurce lag (exp. activity concrteing of slab of 23 days duration 22 days lag and last 1 day conc)while loading buget qty.

When i compare with planned curve and actual curve form p3. Actual shows inaccurate figure ( Exp. i strted activity 30 days back due to some problem it got delayed but we finished 40 % for concrete - keep in mind not concrete just form and steel we need another 5 days to complete) but whn you take resource laoding from updated schedule it give 40 % value, if fact concrete with do after 5 days only what to do.

Replies

Alex Wong
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Check your autocost rule as well

BTW as .mktse suggested, seperate your activity and resources that will help to untangle the mess

Alex
MK TSE
User offline. Last seen 4 years 29 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Instead of resource lag, please consider the resource curve. I create one for concrete - 0% to whole period except the last one. So the curve is "flat" except the last day.

So no actual quantity until the concrete day and same day for the Actual Finish of this activity.