Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual earned quantity!! Not match with real situation!

2 replies [Last post]
Santhosh kumar Na...
User offline. Last seen 6 years 48 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
Hi,
Iam facing a problem. In my program i loaded concrete qty with resurce lag (exp. activity concrteing of slab of 23 days duration 22 days lag and last 1 day conc)while loading buget qty.

When i compare with planned curve and actual curve form p3. Actual shows inaccurate figure ( Exp. i strted activity 30 days back due to some problem it got delayed but we finished 40 % for concrete - keep in mind not concrete just form and steel we need another 5 days to complete) but whn you take resource laoding from updated schedule it give 40 % value, if fact concrete with do after 5 days only what to do.

Replies

Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Check your autocost rule as well

BTW as .mktse suggested, seperate your activity and resources that will help to untangle the mess

Alex
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Instead of resource lag, please consider the resource curve. I create one for concrete - 0% to whole period except the last one. So the curve is "flat" except the last day.

So no actual quantity until the concrete day and same day for the Actual Finish of this activity.