Baseline dates not matching Actuals

4 replies [Last post]
simon davies
User offline. Last seen 9 years 1 week ago. Offline
Joined: 16 Dec 2009
Posts: 9
Groups: None
I have recently taken over another planners P6 programme. I have deleted all existing baselines and trying to take a project initial baseline (the programme has had actuals placed onto it already)

When I assign the new project baseline the dates do not match the Start/ Finish dates. The dates are taking the planned Start/ Planned Finish dates.

Why???

Does anyone know how I can baseline the current project dates, NOT the planned start/Finish dates.

Thanks

Replies

Sunil Babu
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Arnold

Thans for this useful information..

Regards.

Sunil

simon davies
User offline. Last seen 9 years 1 week ago. Offline
Joined: 16 Dec 2009
Posts: 9
Groups: None
I have success!! I got my Admin user to change these settings, and now all dates match actuals! Both my Admin user and myself are very gratefeul. Thank you
simon davies
User offline. Last seen 9 years 1 week ago. Offline
Joined: 16 Dec 2009
Posts: 9
Groups: None
Thanks for your reply. When I try to change these areas, they are grayed out. I have Super User rights and have tried changing settings in WBS, Activity and Project views.

Any thoughts to why this is happening?
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Simon,

Welcome to Planning Planet..

Try to check your Admin --> Admin Preferences --> Earned Value, Earned value calculation, change it to "Budgeted values with current dates".

Regards,

Arnold