Planned % not matching with Actual

please help, planned % not matching with actual % , i dont know how.\

screenshot_2024-10-08_200024.png

[[wysiwyg_imageupload::]]

J
Jerome Odeh 👤 Member for 22 years 6 months

Your screenshot shows the Planned % & Actual % do match where the start & finish dates are the same.

If you are worried that Planned % comes with decimals while Actual % doesn't, it's because the Planned % is calculated using Custom Field formula while Actaul % is a default Microsoft Project field.

This blog post might help you. Microsoft Project Baseline Percent (%) with Weighted Summary Roll-up

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts