Early & Late dates

6 replies [Last post]
Alex M
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 16
Groups: None
Hi, can you run a report in P3 to show the early & late dates for a project?

Alex

Replies

Tahir Naseem PMP,...
User offline. Last seen 6 years 25 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 85
Dear
Please run BC-02 report just
Tool>graphical report>bar charts>bc-02
change in contents tab against dates check box "both"
Regards
Tahir
Alex M
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 16
Groups: None
Hi thanks very much, I ran the SR01 report, how do I respresent this in a grapical report?

Alex
Alex Wong
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Thanks Andrew - and also you can use the graphic report to display it as well

Alex
Andrew Podolny
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Hi

Tools->Tabular Reports->Schedule...->SR-01 "Classic schedule report..."
Alex M
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 20 Mar 2006
Posts: 16
Groups: None
Alex share the wealth?
How do you do it?
Alex Wong
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Yes