Hi.
Basically the situation is I need to do a revise programme, so I used the latest updated schedule, revise and re-baseline it. So from the revised programme, I input new resources as I need to generate S-Curve with 3 main elements which are Planned Early Finish, Planned Late Finish and Actual. I used resource assignment then paste the tabulation in excel.
The problem now is why cumulative remaining late qty tabulated same with cumulative remaining early qty? And the remaining late finish (date) column date is blank. It's like the quantity for late finish used the early finish date, so that's why the tabulation is same.
I already check the late finish date it is later than early finish date. No negative TF. Calendars for that activity is same. No open links. And new data date 1 week was before the early start of the activities.
Is it because before this, the activity should have been started but not started, and now in the revised programme, the activity should not started yet?
If anyone encounter this problem and solved it, please share. I have been googled and found nothing.
Thanks