Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Late Start and finish dates Earlier Than Early dat

2 replies [Last post]
Nishikant Choudhary
User offline. Last seen 20 years 15 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 25
Groups: None
Dear Specialists,
Can you advise me How can the Late dates be Early than the Earlier dates .


I think the problem lies in the Constraints placed or with the Hammock activities.

Please advise , cos the more such anomalies there are the more wayward it drives me towards the TOTAl float and as such the Critical path may not show the true nature of criticality.

Cheers
Bye
Thanks in Advance.

Nishikant

Replies

Nishikant Choudhary
User offline. Last seen 20 years 15 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 25
Groups: None
Thanks Thomas!

Actually Inevitably , i must admit i had this problem of not evaluating the -ve floats properly.although i did envisage a fair amount of the description that you forwarded to me in your reply.

anyway , thanks for clearing my doubt.

Cheers.
Nishikant.
Tomas Rivera
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 2 May 2001
Posts: 139
Groups: None
Nishikant:

I do not quite understand the second part of your message.
Late dates can be earlier than the early dates for an activity. This happens when you have negative total float. Having negative total float means that you are finishing your project later than your imposed finish date. Your late dates show the latest dates you must execute your activity in order to meet your imposed finish date. All this is saying that you must execute the driving activities that are behind schedule, earlier than scheduled (by your early dates) in order to meet the deadline.
In the case you have a constraint that is driving this negative float instead of your imposed finish date, then the above holds true for your constrain finish instead of for your project finish.
If you need to know what activities are driving the project finish, you need to look at a longest path report.

Tomas Rivera