Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Early and Late dates in Ordinal dates

6 replies [Last post]
Joe Mansour
User offline. Last seen 3 years 39 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
Hello everybody,
Is there a way to show early and late dates in Ordinal dates?
For example: Early start: Day 23, Early finish: Day 35

Noting that the P3 calendar uses th notion of workperiod.

Thanks

Replies

Joe Mansour
User offline. Last seen 3 years 39 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
Dear All,

Thank you all for your input.
It is nice to see a subject reopened after over 34 months of my first posting.
Thank you for addressing your postings to me even after this long period.
I will definetely include your turnarounds in my planning hints file.

Please Keep Walking!

Regards,
Johny Kesserwany
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
Hi Joe,

Check your email for detailed steps to display the Ordinal Early Start and Ordinal Early Finish dates. The file contains photos and I don’t know how to paste images in PP!

Regards
JK

NB: If anyone needs these steps, please send me your email.

jkesser@hotmail.com

Mary Folsom
User offline. Last seen 7 years 4 weeks ago. Offline
Joined: 13 Jun 2003
Posts: 10
Try creating a Custom Data Item for the start and finish work period

Then set a column to the custom field created and fill each one in with the information.

I wasn’t able to come up with a global change for you.

You may be able to export the information to move into the CDI

Let me know how it works for you.
Jean-Philippe Sam...
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 7 Feb 2007
Posts: 11
Hi Joe,

One workaround to show the ordinal dates in a layout or report could be to use the date arithmetic feature in a Global Change:

- Create Numeric Custom data items for each ordinal date you want to show (e.g. ORES for Early Start and OREF for Early Finish)

- Create a Global Change (Tools --> Global Change...), and in the ’Then’ portion of the ’Change’ tab, define the ORES and OREF custom data items by calculating the number of workperiods from project start (or any other date):

ORES EQ SD - ES
OREF EQ SD - EF

Of course, you need to manually re-run the Global Change after each schedule update!

Ron, I didn’t know it was not available in P3e/c! Is it back with P6?

Best Regards,

Jean-Philippe
Gene Laratonda
User offline. Last seen 11 years 27 weeks ago. Offline
Joined: 13 Oct 2008
Posts: 3
Groups: None
I would also like an answer to Joe’s question!
Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
P3 only has a Workperiod Line that you can add to a standard report. Workperiods are also shown in the pop-up calendars on the activity tab.

You think that you have it bad - P3e/c (Primavera Version 5) doesn’t have a single place to access workperiods. Not in reports and not in the pop-up calendars! If you need to use workperiod numbers, then stay with P3. Good luck!