Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration Difference - At Completion Duration based on Default Calendar

2 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 15 weeks 4 hours ago. Offline

Hello Everyone,

The is a Difference in Duration in the WBS. The Project Duration is shown as 174 Days and Milestone Duration is 243 Days (which is the calendar days).

5324
wbs_date.jpg

 

I have 3 Types of Calendar in the Project a). 5 Days Work Week, b). 6 Day Work Week and c). 7 Day Work Week.

The Default Calendar of the Project is 7 Days Work Week.

Could you please guide me on how to show in the Project Duration as 243 Days (Calendar Days).

 

Regards

Jithin

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

just make sure that you set a defaul calendar for the PROJECT

Jithin Kambhikanam
User offline. Last seen 15 weeks 4 hours ago. Offline

HI Everyone,

 

Got the Answer after doing some research,

 

I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week.

Now the Total Duration is same as the the Below WBS Duration.

 

Regards

Jithin