Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Impact of Global calendar vs Activity based calendar

3 replies [Last post]
Farhan Aftab
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 8 Aug 2018
Posts: 3
Groups: None

Hi Guys,

If a programme has a default Global calendar with two days a week off ( sat/sunday), and it is ticked as default in calendars. But, the individual activities have three different calendars, 6 days a week, 7 days a week and the default one, stated above.

Which one takes precdence in scheduling? What is the difference between default calendar and then choosing separate activity based calendars?

Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Farhan Aftab
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 8 Aug 2018
Posts: 3
Groups: None

Thanks Zoltan ; Noted.

Zoltan Palffy
User offline. Last seen 3 weeks 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

NONE take precedence its whatever your calendar  that the activity is assigned to. BY design when adding a new activity will automatically be assigned to the calendar listed in the defaults tab which is in the projects directory