Program to complete works beyond the Contractual Time to Complete.

Member for

19 years 10 months

Hi Jose

It is the same thing - He is not going to complete in time so he must issue a "Revised" programme.

Best regards

Mike T.

Member for

18 years 5 months

Thanks Mike for the reply.

Clause 8.6 calls for a Revised Program to complete the Works within within the Time for Completion.

Here, the Time for Completion has elapsed... True, we need a program to know when the contractor would complete the Works.  But can we call this program a 'Revised Program'?  

Best Regards,

 

Jose

Member for

19 years 10 months

Hi Jose - Welcome to Planning Planet

You do not tell us which of the FIDIC books you are working under but the principle is mostly the same.

This is from the Red Book 1999.

1. Issue a Notice of Non Completion under 8.7 stating that LD's will be deducted.

2. Require a revised Programme under 8.6.

Best regards

Mike Testro