Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Estimated completion time

17 replies [Last post]
steve willis
User offline. Last seen 18 years 5 weeks ago. Offline
Joined: 12 Aug 2004
Posts: 7
Groups: None
We all know that Computer schedulers work out the estimated completion time of a project .But for piece of mind can anyone tell me a simple formula that you can use to work it out.

Replies

Wilmore Makonese
User offline. Last seen 18 years 45 weeks ago. Offline
Joined: 26 Sep 2005
Posts: 12
Groups: None
GOOD PLANNING CLIVE, THAT’S THE ANSWER TO THIS QUESTION AND OF COURSE THE OTHER SUMMARISED BIT BIT FROM SAKAMURA... FROM MALASIYA.

OR THE VERY SUMMARISED: EXPERIENCE & EXPOSURE - WHICH WILL SHOULD GIVE YOU ALL THE RATES & TIMESCALES NEEDED TO COME UP TO COME UP WITH AN ESTIMATE.
Oscar Wilde
User offline. Last seen 16 years 40 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 166
Groups: None
Here here clive
Clive Randall
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
I am getting the urge to break into capital letters.

Yes the Client decides the Project duration sometimes based on factors beyond those the contractor is aware of.

However read what i said earlier

At the time of tender it is the planners responsibility to make sure the contract period can be achieved and allow sufficient resources to achieve it even if these resources are un-economically utilised. He must advise the estimator what he has done.

If after all this he still cannot find a way to achieve the contract period he should advise the overun so that the estimator can allow LDs .

A very foolish Company assumes the period is achievable without checking at the time of tender.

As for claiming an EOT this has little to do with whether the contract period was sufficient. You will certainly NOT get and EOT because the period proves not to be sufficient.
at a later date.

Carpe Diem (or similar)

If you are saying because of insufficient information it is impossible to check then you can either qualify your tender or make educated assumptions. These require experience and this is where your senior planner or planning manager will come into his own.

kind regards

Clive Randall
haslan abdrahim
User offline. Last seen 19 years 6 weeks ago. Offline
Joined: 18 Aug 2004
Posts: 4
Groups: GPC Malaysia
i think client always imposed completion of the project during tender stage and normally the contractor will schedule the projet to complee within the time imposed by the client in that way chances to win the job is higher. in reality during construction contractor realizes that the time given is too short and endup of applying for eot.
so any comment?
regards
Rolyn Jalea
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 2 Jun 2004
Posts: 34
Groups: None
hi,

Sometimes it sad to say that by the time a planner goes to work on a schedule, the planned start and finish date is already approved in the contract. There’s no way he can do about it but to maximize as much as possible the alloted duration based on the contract.

Regards,

Rolyn
Zq qz
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
EXPERIENCE .............. AND EXPOSURE ........
Charleston-Joseph...
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Clive,

In the planning engineering way, the approach in estimated completion time is reasonable.

In reality, client do have the final say on the project completion time.

Some project duration during the tender stage maybe unrealistic, but at the end of the day, what project duration agree and stipulated in the contract is an obligation of the contracting parties.

Cheers
Clive Randall
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Sorry dont agree either with you Mr Zang or Raja
This to me is the planning rub
We allow clients to determine what they want and therefore programme for that whether it is possible or not
thats fundamentaly flawed and if not picked up leads to contractors paying damages or acceleartion costs which they do not have in their budgets.
I believe that a rule of thumb exists.
However if you really want to know how long it will take i would suggest the following. Work out when you will have the builders work drawings cast ins etc. Work out how long it takes to do a floor (not so easy but the subject of another thread), multiply that by the number of standard floors, add in the non standard floors, see when you can start the cladding (not just on structure status but also on material delivery), Schedule when you can do the finishings. Allow 4 months for the roof top plant rooms a further 2 for commissioning.
Press the button and see where the path lays on high rise it will be up the structure through the toilets, lifts and plant rooms and out through the front reception and external works.
If it dosent sit with the contract period review the critical path and see what you can do with it. More cranes more people, more formwork. Concentrate on the structure as it usually the easiest to accelerate (less trades). Having done all that see where you are. You would be suprised how little difference all the manipulation you do makes even when you try to manipulate the critical path.
Remember to take a day off on a floor cycle costs a fortune and on a thirty storey building saves you only a month.
Also remember factors that despite money or time cannot be accelerated, offshore deliveries, concrete strength gain, flushing of mechanical systems, anything to do with Govenment.
If the answer is not what the client wants to hear add the damages into your price and tell him it can be completed in his timescale.
Whatever you do dont believe the client has the right timeframe until you have checked it and taken appropiate measures to ensure it can be achieved.
You may find that you can do it quicker than he wants it so you can reduce your prelims. Thus winning you the job.
Thats what planners are for. Well thats what i think there for to prove beyond a reasonable doubt how feasible the time element of a project is.
Despite all this I believe there is a rule of thumb for how long a building will economically take to build.
Raja Izat Raja Ib...
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Mr Zhang,
If u were contractor, 100% agreed, but for client maybe they have to think The best date to Come out with the product. The best date is when the product price at that time rising Up.
Zhang Haixiang
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
the completion time highly depends on the requirements of the client( time & budget),so there is no such a formula

Clive Randall
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Steve
I reckon Sukaraman is spot on
The rule of thumb is pretty close to the outurn time for a building
Obviously u need to conside and requirements from Government authorities etc
For those who dont believe there is a rule of thumb have a think about how a project period contract period is arrived at. Usually by a client who knows what he wants and approximatly how long it has taken before.
Raja Izat Raja Ib...
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
use production rate per square meter and apply to the design u can get:
a. estimated resource
b. estimated manhours
c. estimated cost
d. estimated scedule

this production rate, u can extract from previous project and to get good productivity, u have to analyse closeup report(lesson learn)...if u have.
Sukumaran Subaram...
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Steve,

As for highrise building:
1) Get the productivity for one floor i.e. for structural works. Use this productivity rate and calculate the overall structural completion date.
2) Check when the contarctor can start the M&E and Architectural Works. The contractor shall be able to complete the work approximately six months after the structural completion date (depend on size of the project).
3) Then calculate the duration for External Works, Final Cleaning and Hand Over.

HTH.
Edgar Ariete
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
Hi Steve,

May I suggest: A) Strategy + Practicality + A lot of Prayers....

You said Estimated... that’s a GUESS...

If you want it accurate...You measure it. Use any machine.


regards,

Edgar
Charleston-Joseph...
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Steve,

There is no such things as simple formula in arriving at estimated completion time.

The danger of using simple formula is the consequence of your professional reputation.

In my younger days, i did hear a lot of old folks guessing the estimated completion time base on their previous projects experience and interpolating those experiences with the projects at hands. They just remains guess. There is no substitute to hard work and engineering approach to arrive at estimated completion time.

I hope this will help you going somewhere

Cheers,

Charlie
William Cormack
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 24 Apr 2001
Posts: 21
Groups: None
I had a quick look at the APM’s EV Guidlines and it gives the following equation:

Forecast Completion (In weeks from original project start) = Original Completion/SPI.

It’s also worth looking at Appendix D of that document.

I make no comment on the validity of these formulae.
Katalin Hovanyi
User offline. Last seen 10 years 21 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 38
Haliho,
The reason for the risc analisys that nobody can be sure. Formerly the fortune tellers did the job but we became modern and the planners got this thankless task. Steve, an advice. Use as much Finish to Start connection as You are able and when the project ongoing and whenever You get the resources and the workplace go paralel. In that case, MAYBE (it is a big maybe) You can get the originally estimated dates (or a more or less near one).
Best Regards
Katalin