Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to set delivery lead time in gantt

6 replies [Last post]
Eugene Y
User offline. Last seen 8 years 52 weeks ago. Offline
Joined: 18 Mar 2016
Posts: 3
Groups: None

Hi,

 

Good day to all.

In scheduling, when I have a scenario whereby I purchase an equipment from vendor, and need to wait for vendor to deliver it, should this wait time be set as a task with the duration being the same as the delivery time, or should I use a milestone with a lead time dependency?

 

cheers

Replies

Jithin Kambhikanam
User offline. Last seen 25 weeks 3 days ago. Offline

Hi Raymund,

No issues. Your Sujjestion is takne into account but I would prefer a schedule to be a little detailed so as to know whose fault it is Vendor, Contractor or Client which you cannot know by putting just a Milestone (Who is responsible for the Milestone).

 

Regards

Jithin

Raymund de Laza
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Jithin,

My concern is in updating the Manufacturing progress. During those period of Manufacturing when there is need to update the Schedule then the Progress will just be computed as number of days passed vs remaining days.

My Suggestion as Milestone is that the Contractor just wait for the delivery Date and if arrived then update the schedule accordingly.

Just a suggestion.

Jithin Kambhikanam
User offline. Last seen 25 weeks 3 days ago. Offline

Hi Eugene,

I (Contractor) work on EPC projects and I split the Procurement Task according to the Material as its all by different vendors example,

Pump

Tanks

Generator

Pipes and Fittings

Cables

Instruments

etc.

We split it according to Material (Vendors) so as to monitor which item is delayed and what will affect the Project completion. Whom to Push like usually Bid Evaluation Award (Contractor), Manufacturing (Vendor) and Delivery (Contractor).

So by spliting it up we can Alert as to whose part is the delay is The Vendor , Client or Contractor.

Hi Raymund,

Usually Manufacturing and Delivery Period can be monitored as the Vendor would say that example They need 22 Weeks for Manufacturing and Delivery (Usually by the one who places Purchase Order - Contractor) can be monitored like we (Contractor) on gerneral note know that it would take a minimum of 6 Weeks of delivery from USA or EUROPE to Middle East.

So we would know when the Manufacturing and delivery would be finished. We can Alert our team (Procurement) to look at if its finished and is it shipped. All this points would defenitly help you out.

Regards

Jithin

 

Raymund de Laza
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

I suggest to use a milestone for the Delivery date needed prior to Installation/Execution. Then use ALAP constraint.

Manufacturing and Delivery Time Period can not be Monitored.

Eugene Y
User offline. Last seen 8 years 52 weeks ago. Offline
Joined: 18 Mar 2016
Posts: 3
Groups: None

Hi Jithin,

Thanks a lot! Sounds advice that goes beyond what I have expected to get.

So, I should make task by vendor a task.

To think further on it, is there any disadvantage to use set lead time on milestone for delivery date?

Thanks.

Jithin Kambhikanam
User offline. Last seen 25 weeks 3 days ago. Offline

Hi Eugene,

Its better to put 3 task for a procurement item as minimum.

1) Bid, Evaluation and Award 2) Complete Manufacturing and Final Inspection 3) Delivery - Delivery duration is the time to ship / airlift or any means of transportation of material from the manufacturing location.

One more option is which is little bit more detailed,

1) Prepare / Issue MR 2) Recieve Bid 3) Complete Technical Evaluation and Submit TBE for Company Approval 4) Receive Company Approval 5) Issue FOA / FOA/Letter of Award 6) Manufacturing 7) Delivery

With this you can properly monitor where the delay is and what is the effect. RegardsJithin