Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

What are the ways to adjust Out-of-Sequence Activities in your project ?

3 replies [Last post]
Arslan Shahid
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 13 May 2015
Posts: 13
Groups: None

What are the ways to adjust Out-of-Sequence Activities in your project ?

 

Do we need to change the relationships, if it does then how to make these changes in a baseline ? please help me with the procedure.

 

Thanks in advance.

Replies

What are the ways to adjust the out of sequence activities in a project, please choose the kind of activity like a physical,duration and units. Convert the activity into the phyiscal percent complete.

 

When scheduling use the progress override options in scheduling tab....

Arslan Shahid
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 13 May 2015
Posts: 13
Groups: None

Dear zoltan palffy,

 

Thank you very much. You explained it brilliantly.

 

Regards,

Zoltan Palffy
User offline. Last seen 7 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I agree with Andrew

You usually change the logic to account for out of sequence progress.

You never ever change the baseline this was your original plan an your concept of how the project was going to be performed.

As you update the schedule things change for whatever reason and you are forced to do things differently hence the out of sequence progress. 

Why in the world would you want to go back and change or baseline logic based on things that you had no idea were going to happen.

The WHOLE purpose of a baseline is so that it can be used to compare the original plan to the current plan and note the differences. 

What you want to do is like originally planning a trip from New York to Los Angeles to drive it in 4 days = Baseline

Now something happens along the way and you have to stop in Miami first then from Miami you can proceed to Los Angeles this now adds 1 more day of travel time to your trip make it 5 days instead of 4 days = Update and out of sequence because you added the stop in Miami.

So with the basline line logic and sequence intact you can see that it originally was going to take 4 days for your trip but due to the added stop in Miami it is now going to take 5 days to complete your trip.

If you go back and change the original plan to include the added stop in Miami how could you ever compare the original plan vs the current plan ? You could not do it.

The baseline is your measuring stick NEVER change it. 

Andrew Pearce
User offline. Last seen 1 year 49 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175

In my humble opinion you have to make changes to relationships in the current version of the schedule. This is to reflect the actual sequence in which works were executed. You do not cahnge anything in the baseline.

The baseline being what you originally planned to do and the current version being what you actually did.