Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updating schedule

4 replies [Last post]
John K. L
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 23 May 2015
Posts: 2
Groups: None

Hi guys,

I'm a construction management student and asked to do an assignment about "Updating Schedule", so what is meant by Updating Schdule in project management, and what is the purpose of updating schedule?

 

Regards

Replies

Zoltan Palffy
User offline. Last seen 2 days 24 min ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

While Patrick's references may be helpful the links do not work. I have stated the basic concept.

Rafael Davila
User offline. Last seen 1 week 2 days ago. Offline
Joined: 1 Mar 2004
Posts: 5240

For cost loaded schedules please take a look at the following reference.

http://www.nflaace.org/index_files/john_orr_cost_loaded_schedule_updatin...

Patrick Weaver
User offline. Last seen 20 hours 45 min ago. Offline
Joined: 18 Jan 2001
Posts: 382
Groups: None

Zoltan's comments below are structurally correct, but there is more to updating than simply processing information.  This paper from 2002 is still current: Managing for success - the power of regular updates: http://www.mosaicprojects.com.au/PDF_Papers/P002_MFS_Full.pdf 

For more on the overall process of developing and maintaing a 'good schedule' see: http://www.mosaicprojects.com.au/PDF/Good_Scheduling_Practice.pdf 

Zoltan Palffy
User offline. Last seen 2 days 24 min ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

updating a schedule is when you apply progress to your schedule thru a certain date. An activity can be in one of three stages

not started

started (but not finished) = in progress

or finished - completed 

What you do is indicate any activities that have started recored the actual date they have started. If they are not finished you input the remaing duration for the activity to complete = in progress

You also record any activities that were previously started and have now finished and you indicate the actual finish date.

You also recored any activities that have started AND completed during the reporting period and indicate theri actual start and finish dates

You would also add any new work or change order work that ws issued to you. 

You then chnage the data date (PROGRESS THRU DATE) and recalculate the schedule.

The purpose of this is show where you are on your project either being on schedule, ahead of schedule or behind schedule.