Hi All,
Please help me, i am a rookie on this planning and schedulling.
I have a schedule that need to be updated against the baseline/Target,i need to know the best method of updating, comparing to the basline & forecasting the completion.
I usually input the percent complete and RUN (with unlink remaining duration to percent complete)then i reduce the remaining duration by 7 days (the working days in a week)so at least the target finish of an activity will be the same as basline. But how about if the activity suppose to finish but it has not finished, how we determine the remaining duration?
2nd scenario, i RUN another copied file with (Link remainning duration with PC) and let the software forecast the end date. but the remaining duration in this methode will jump if the period % complete is under expectation.
I hope my question is not to confusing.
Thanks All.
Replies