Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Producing Baseline S-Curves even after some activities were started/finished

1 reply [Last post]
Romil Villanueva
User offline. Last seen 5 years 23 weeks ago. Offline

Hello my dear fellow planners.

I would like to ask some assistance, I am having a hard time plotting the late and early curves of my schedule (Primavera  v6.2).

The situation is that, during FEED phase, EPC Schedule was drafted and some of the activities on FEED Phase were used as

predecessors for EPC so now that I am setting up the S-Curves for progress monitoring, I am having difficulty because I want to set

the Zero-Point / Start-Off point of EPC Progress Monitoring specifically from the activities which were started but at least not finished.

Is this possible?, setting the zero point on the middle of the ongoing activity?

 

Thanks, merry christmas and happy new year.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 10 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes just take the scheduel and de-status it and change the data date to the start date and recalculate the schedule