Change must end by date

1 reply [Last post]
Dave Scott
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 12 Dec 2011
Posts: 4
Groups: None

I recently built a schedule in P6 that had an must end by date of July 23, 2012.

Shortly there after, additional work and time was added to the project.

How can I add the 6 extra weeks to my schedule?  I need to move the must end by date out by an additional 6 weeks.

Thanks,

Dave

Replies

Gary Whitehead
User offline. Last seen 5 years 30 weeks ago. Offline

Dave,

 

From Enterprise > Projects, highlight the relevant project.

Then go to View > Show on Bottom > Project Details

Go to the "Dates" tab of the Project Details, and you can ammend your Must Finish By date here.

 

Cheers,

 

G