Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project completion date changing

3 replies [Last post]
abdul subhan sidd...
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 13 Feb 2013
Posts: 4
Groups: None
Dear all I need help ... My contractor suited a programme which was last updated on 15 jan 14 and now I have updated all the percentages of the programme and when I am hitting f9 to the 24 den as data date the project completion date is changing . Please help.

Replies

R Voneister
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 1 May 2014
Posts: 5
Groups: None

Abdul, It is such a basic thing that its surprising you actually asked such a question. 

If you don't want the completion date to change make sure you perform the planned work in the allotted time.

Muhammet Koçak
User offline. Last seen 10 years 38 weeks ago. Offline
Joined: 1 Mar 2014
Posts: 2
Groups: None

Also I have same problem I thing. Problem is that. For example, I have one activitiy and it's finishind date 25 march 2014 and data date is 10 march 2014 so remaining date must be (it can be changed depend of calendar) 15 days. I updated Data date to 20 march 2014. after updated remaining days still be 15 days and completion date go to 30 march. How can I fix it ? Urgently

Gary Whitehead
User offline. Last seen 5 years 24 weeks ago. Offline

What's the problem?

Completion date should change if the project does not progress exactly to plan.