Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

What are the 'must have' Period End Reports (Non Cost / Resources loaded)

1 reply [Last post]
Philip James
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

Hi

 

What are the must have period end reports, I would be advised to produce

Currently, I receive our contractors programme, and produce the following reports

1. Full Programme, with Last Period and Baseline Variances

2. Critical Path Layout

3. 4, and 8 week lookahead

4. Milestone Slippage

 

The programme submitted is not cost or resource loaded.

 

Regards

Philip

Replies

Zoltan Palffy
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

total float report and a schedule narrative