Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 - Using the Global Change funciton to remove 'Actual' Dates'

6 replies [Last post]
Danny Fitzgerald
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 9 Dec 2008
Posts: 4

Hello Chaps

I need to remove all 'actuals' from the start and finish date columns. I wish to retain the previously designated actual dates so that they now become the schedule 'plan' dates.

 

Can this done using the global change function?

 

Thanks in advance

 

Dan

Replies

Shareef Abdul Azeez
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183

Hi Danny ,

 

  • You can remove progress of activities in a  programme, but to retain the Actual dates and the new Original Durations, you will have to change your links to bring those (Actual) dates on the  non progressed (Baseline programme).

 

 

Best Regards

Shareef A Azeez

Haitham Khaireldin
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 36
Groups: None

Hi Michael,

No you cant change the data date to an older one.

Krishna Kumar
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Feb 2007
Posts: 25

Hi Danny,

              Why can't we try to save it as second baseline as we do in P3, so that all the actual dates becomes as scheduled plan & then you remove all the actual dates. Jus try it.

 

Regards,

V S Krishna kumar

michael ramos
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

hi haitham

why do you need to create a new file and then copy paste? can't you change the data date to original data date and run?

michael ramos
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

if Activity Status not equal Not Started

then Activity Status EQ Not started

note:

if you have resource units already progressed, make them zero first by global change or assignment columns

Haitham Khaireldin
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 36
Groups: None

You can do the following:

Make a Global Change function in the then pane with AS EQ " " and AF EQ " " and PCT EQ 0

But you will face a problem, which is that you already have progressed activities which means that the data date has an advanced date over some/all activities. So if you followed the above cited instruction you will have your project unprogressed but not matching with the original dates. So you have to make a new file with a project start date same as your original file, copy all the activities from the original file and paste them in your new file then follow the above instruction.

Note: Dont transfer the old calender in your new file as that will change the data date again. Create a new one