You can remove progress of activities in a programme, but to retain the Actual dates and the new Original Durations, you will have to change your links to bring those (Actual) dates on the non progressed (Baseline programme).
Best Regards
Shareef A Azeez
Member for
18 years 9 months
Member for18 years9 months
Submitted by Haitham Khaireldin on Sat, 2010-11-13 10:34
Why can't we try to save it as second baseline as we do in P3, so that all the actual dates becomes as scheduled plan & then you remove all the actual dates. Jus try it.
Regards,
V S Krishna kumar
Member for
16 years 8 months
Member for16 years8 months
Submitted by michael ramos on Fri, 2010-11-12 03:48
Make a Global Change function in the then pane with AS EQ " " and AF EQ " " and PCT EQ 0
But you will face a problem, which is that you already have progressed activities which means that the data date has an advanced date over some/all activities. So if you followed the above cited instruction you will have your project unprogressed but not matching with the original dates. So you have to make a new file with a project start date same as your original file, copy all the activities from the original file and paste them in your new file then follow the above instruction.
Note: Dont transfer the old calender in your new file as that will change the data date again. Create a new one
Member for
20 years 1 monthHi Danny , You can remove
Hi Danny ,
Best Regards
Shareef A Azeez
Member for
18 years 9 monthsHi Michael,No you cant change
Hi Michael,
No you cant change the data date to an older one.
Member for
18 years 8 monthsHi Danny, Why
Hi Danny,
Why can't we try to save it as second baseline as we do in P3, so that all the actual dates becomes as scheduled plan & then you remove all the actual dates. Jus try it.
Regards,
V S Krishna kumar
Member for
16 years 8 monthsif Activity Status not equal
if Activity Status not equal Not Started
then Activity Status EQ Not started
note:
if you have resource units already progressed, make them zero first by global change or assignment columns
Member for
16 years 8 monthshi haithamwhy do you need to
hi haitham
why do you need to create a new file and then copy paste? can't you change the data date to original data date and run?
Member for
18 years 9 monthsYou can do the following:Make
You can do the following:
Make a Global Change function in the then pane with AS EQ " " and AF EQ " " and PCT EQ 0
But you will face a problem, which is that you already have progressed activities which means that the data date has an advanced date over some/all activities. So if you followed the above cited instruction you will have your project unprogressed but not matching with the original dates. So you have to make a new file with a project start date same as your original file, copy all the activities from the original file and paste them in your new file then follow the above instruction.
Note: Dont transfer the old calender in your new file as that will change the data date again. Create a new one