Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changes Dates Automatically P6

5 replies [Last post]
Felipe N G
User offline. Last seen 16 years 15 weeks ago. Offline
Joined: 17 Apr 2008
Posts: 6
Groups: None
Hello everybody,

In Microsoft Project when i change the date of one activity the others activities change the start date automatically, but in P6 i can´t.

I go to Edit/User preferences and click Reorganize automatically, then press F5 and the activities don’t change.

So i choose the chart view, select all activities, right click/ reorganize all and the activities don’t change.

Tools/Reorganize now and nothing.

Any can hepl me please?

Regards,

Felipe

Replies

Anoon Iimos
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422

try F9

ECHEZONACHUKWU OB...
User offline. Last seen 5 years 47 weeks ago. Offline
Joined: 31 Aug 2010
Posts: 9

Felipe,

 

P6 is more suffiscated than MS so, it depends on the relationship that exist between the activities you are talking about. that's the only thing that would make them change automatically when you change the date of one activity and schedule. Pressing F5 to refresh can only make a reorganisation you made in P6 to take effect if it is hanging. this even better for you so that you would be sure of every input you make.

Regards,

Eche

Dieter Wambach
User offline. Last seen 7 years 28 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Carmen
Thanks for the compliment, but I learn much more in this forum than I can give.
Because it’s just by chance, if real life exactly meets the plan I prefer manual updates. But until now I couldn’t find any bug in this function. So to my opinion it would be possible and faster for some projects, to use spotlight --> update progress --> adjust variances.

Regards from Germany Con un cordial saludo
Dieter

Carmen Arape
User offline. Last seen 7 years 11 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
Felipe,

Dieter is right (almost always). You can do the set up of schedule options. Puedes definir opciones de calculo de schedule.

Dieter,

have you ever used the following options in order to speed up the boring update process. Options are: progress spotlight and Update progress. Really good for updating but I got some dates out of control.

Cheers,
Dieter Wambach
User offline. Last seen 7 years 28 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Felipe
In P6 it is "F9" or Tools --> Schdule or the icon. There under "Options" you can select "Schedule automatically..."
By experience it’s better to schedule on only request - that’s why it is an option in MSP as well.
Regards
Dieter