Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

When Is the Time To Ask For Recovery Schedule?

5 replies [Last post]
AB Timo
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hi all,

I have a Question about the Criteria That should be kept in Mind for asking the Contractor about the recovery schedule,

Lets say that the Delay is Totally on the part of Contractor and no EOT claim.Please tell me that What Criterial Of Percantage should be kept in mind.I mean to say that how much Actual % would be Lesser than Planned % when there will be a need for the recovery Schedule??? 4%,5%,6%...???? Any Criteria??

 

Regards,

Replies

jingjun zou
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 8 Apr 2008
Posts: 6

Rafael Davila, your provided file is very useful, thank you.

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

AB,

 

The real answer to your question is, “What does your contract say?”  If it does not mention this, then you may have the right to ‘ask’ but probably not the right to ‘require.’  It is very important to ask your management about this before proceeding further.

 

There is a second consideration here.  Even if you have the right to ask, this does not necessarily mean that the contractor must accelerate their operations for free.  Submitting a proposed recovery schedule does not ordinarily commit the contractor to actually performing the adjusted work schedule.  You asked for a revised plan and they gave you one.  Now you have the opportunity to decide whether you want to pay any additional costs to have the plan executed.  Good luck!

Aidan Kelly
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 5 May 2011
Posts: 24

Hi Ab Timo

Agree with Shauhul.

A compotent contractor would realise that they are exposing themselves to LD's and look to recover against the milestones. The client would then review the master schedule and make the decision to request a recovery proposal based on the overall progress.

It is also discipline specific (not sure of your exact situation). For instance on a large scale Oil and gas or similar multi-discipline project, if mechanical was delaying electrical but in turn was delayed by Civil there may be little point in asking electrical or mechanical to recover delays and be hit with a disruption claim because of congestion/access issues etc.

Civil would need to recover their delays or accelerate and good planning would spot this befored it started to delay the entire project.

In essence the earlier the better 2-3% as dependant on the size of the project and number of contractors on site this could translate into weeks. Reschedulling activities & clever planning can recover a few days maybe a week but several weeks will require acceleration to the meet the milestones.

 

Hope this helps a bit.

Aidan

Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi AB Timo 

I am not sure about the criteria used for recovery schedule ,but in general if contractor performance  found to be slipping  ,then it is obligation of contractor to do recovery schedule to meet the contractual finish date/Milestones

Cheers

Shahul