Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Best way to either require or get TIME contingency in a schedule? I mainly know the cons...

No replies
John Reeves
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Best way to either require or get TIME contingency in a schedule?   I mainly know the cons...

There will be delays on a big project, it seems like you are setting yourself up to pay more:  some thoughts?  I was on a job once where they accidently have 4-5 months too long.  You never had to worry about time claims and the contractor still wanted to get out as fast as they could to avoid overhead etc costs.  I guess you could get a contractor that would use it for fill in work and drag it all the way out - longer than needs to be.

If you don't need it for 16 months, require the Completion in 14 months, but budget in paying for contractor Overhead for the extra two months.  If you make that part of general contingency someone will snatch it for something else.

Other methods that I think are a problem.
.1. Two month reserve at the end.  No, that will mess up your floats everytime you release some reserve, you need limited new dates.  Plus that reserve effects construction activities but should not for weather - but a reserve at the end will add float to submittal items etc that should not have any.

.2.  Require 2 months float.  People dislike a schedule that has 60 days float critical paths.  People are used to seeing or wanting the critical path at 0.  If it were for just schedulers that is one thing, but it never is.

.3.  Have a regular substantial completion date, but a final completion date with 2 extra months it, then award SC early with some of the items sliding to Final Completion?

.4. Your idea:

Peter Holroyd
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 6 Jun 2005
Posts: 162

John,

corporate directive

- all schedules should be 90% of contract time with TRA added!

- Float should be spread evenly along the EPC path.

Peter