Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

DEFINITION OF ACTIVITY SEQUENCE IN MEP WORK

10 replies [Last post]
Vinay Goel
User offline. Last seen 13 years 32 weeks ago. Offline
Joined: 29 May 2009
Posts: 6
Groups: None
Hi, As im am working with MEP & Fitout planning. I have regular discussion with Project Manager about the definiation of First Fix / Second Fix/ Final Fix for Electrical, HVAC, Plumbing & Fire Fighting work.

The practical idea behind these fix is to make the Cluster of activities which requier resources of similer skill sets and Status of Interior.

Is there any official defination of "Fixes " for these services in any building codes / Standard ( In UK / US etc)

Replies

Jithin Kambhikanam
User offline. Last seen 15 weeks 4 hours ago. Offline

Hi Vinay,

I had worked as Planning Engineer in the MEP Field before so I will tell you what I learned. In MEP  we had the following section by which we monitor the progress.

  • Slab Work - Any Work on the Slab - like Electrical Conduit Laying, Sleeve for Pipes and Ducts.
  • MEP 1st Fix - Anything on the Blockwork before Plastering - usually Pipework, Conduiting, GI Box, Sleeves, Drainage Work in Toilet, Kitchen after which the plastering would be done.
  • MEP2nd Fix - Anything beffore the false ceiling is done - like Wrire Pulling, Support Work, Pipe Work - Water, Drainage, CHW, Including PRessure Test. Water HEater Instalaltion, GI Conduit, Cable Tray , Cable Pulling, Fire Fighting Pipe Work, FCU fixing, Ducting, DB , MDB Wiring and Termiantion
  • MEP 3rd Fix - After Flase Celing is Done - Light fixture Installation, Switch Board, Grills & Diffusers for HVAC, Toilet Fixtures fire fighter sprinklers and all other finishing works.
  • Pre-Commissioning
  • Commissioning

Regards

Jithin

Mohammed shujauddin
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 18 Apr 2016
Posts: 2
Groups: None

Hi,

I am working as planning engineer,i am new in this feild.

My consultant asking me planned % and actual acheived % of work. after updating in primavera schedule i am getting planned % but how to get acheived % of work.  i tried in primavera, i updated physical % manually ( the work which completed at site in percentage) but over all % i am not getting.

can any one know about this.

Balu Karunakaran
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 16 Dec 2007
Posts: 32
Dear Samer

Thats true.But what I meant is that there is a lack of standardisation in the MEP sequencing as such it seems.

Regards
Balu
Samer Zawaydeh
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Balu,

As long as the team members know exactly what is mean by the description of each activity, you will be ok.

With kind regards,

Samer
Balu Karunakaran
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 16 Dec 2007
Posts: 32
While I was engaged in 2 different projects the fixes were different for each .

It is really a controversial issue.
Jacob Emmanuel
User offline. Last seen 10 years 26 weeks ago. Offline
Joined: 7 Nov 2008
Posts: 14
Groups: None
We are using:

HVAC SYSTEM

1st Fix - Ducting and Insulation, All Piping Works (Drainage, Water Supply, Chilled Water, etc

2nd Fix - FCU and Connections & All Testing

Final Fix - Grilles, Diffusers, Water Heaters & Sprinklers


ELECTRICAL SYSTEM

1st Fix - Conduiting & Enclosures

2nd Fix - All Wirings, Treys & Trunking, DB’s

Final Fix - Smoke Detectors, Light Fittings & Switches

SHAJI MOHAMED
User offline. Last seen 14 years 6 weeks ago. Offline
Joined: 10 May 2009
Posts: 14
Groups: None
Dear Sirs,

This is very interesting topic. u know when i started my carrier before 1 year my seniors explained one type of definitions for each fixes. Now the scenario had been changed into some other.

For Example They explained me that 1 st fix means Inside slab works or u can say in-cast services(conduiting,pipe openings,sleeves,duct openings)and also support fixings, trays & trunking works....

2nd fix defined for Duct instln,CHW Piping works,cable laying,water& drainage piping works,FF piping works, MEP Equipments instlns like (chillers,AHUs,FAHUs,FCUs,cooling towers,fans,MDBs,SMDBs,DBs,Panel Boards,DG Set,Transformers,Switch gears,Heat Exchangers,Water Tanks,Droppers,water heaters,Pumps,etc....)

Final fix includes Installation of Grills & Diffusers,Light fittings,Smoke detectors, Sprinklers, Taps, Sanitary ware fittings etc......(which is visible to the visitor mostly)

But these definition are being modified or considered based on the project team of client/consultant,MEP COnsultant,civil contractor,MEP contractor... Somebody will consider In-cast services only as 1st fix works.

Then all support fixings and sleeves as 2nd fix with above mentioned 2nd fix definitions.

So can you pls tell me,,, is there any proper definitions to identify these Terminologies in the proper manner.

Many Thanks in advance.....

Regards,

S.Shaji Mohamed


Samer Zawaydeh
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Vinay,

The best idea would be to agree with your team members on the definition of each. This is not a big issue.

Make a list of all the systems that you have. Depending on your project, you might have from 2-16 systems. For each system define what is the meaning:

1st fix: install conduits in concrete or empty conduits anywhere.

2nd fix: pulling wires for electrical systems and installing valves flush with finish surface for mechanical systems.

3rd fix: install sockets, and cover plates, and lighting fixutres for electrical systems, and installing the fixtures or machines for the mechanical system.

Commissioning is a stand alone process since you will need the whole system operating at many zones.

Hope that the information assisted you. I did inquire from a Mechanical Consultant about the definition in the code, but I had a negative reply.

With kind regards,

Samer
PINAN T.
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102
Mike Testro
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Vinay

I have moved this thread to this forum.

You will get a better response from here.

Best regards

Mike Testro