Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

mep sequence in building

1 reply [Last post]
Johnny Wee
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 23 Jul 2007
Posts: 21
Groups: GPC Qatar
just share your ideas,need to complete the following:

electrical
wall:
after blockwork chasing/marking,we can start for conduiting and g.i. box and db box then close by plaster.. then we install wiring for light and power..then install/terminate db after light fittings

ceiling:
after blockwork, install hangers then g.i. tray then high level wiring install, then access for ceiling works

a/c

after blockwork, we can start for 1st fix a/c hanger then start ducting / insulation and fcu and chilled pipes installation in parallel, then connect line bet fcu and duct,then access for ceiling works

after fixing of pipes, testing/commission

Replies

Samer Zawaydeh
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Johnney,

It depends on the size of project that you have. Either go by

1st fix electrical: Walls, ceiling and Floor
2nd fix electrical: pulling cables and wires,
3rd fix electrical: sockets, cover plates, lighting fixtures and commissioning.

1st fix Mechanical
2nd fix Mechanical
3rd fix Mechanical: installing fixtures, pads and commissioning,

for big size project, it is preferred that you go by system. For MEP, it can run between 15-25 systems.

Let me know if you have a more specific question.

Best,

Samer