Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delay Analysis - Windows Analysis Method vs. Time Impact Analysis (TIA) or Time Impact Evaluation (TIE)

7 replies [Last post]
Kristopher Coronel
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 16 Feb 2009
Posts: 7
Groups: GPC Qatar

Hi Guys/Gals,

I have a confusion about the difference between Window Analysis Method and Time Impact Analysis and also about Time Impact Anaysis and Time Impact Evaluation when use in Delay Analysis.

Please maybe some body out there can explain this jargons.

Thanks.

Replies

Ali Osama
User offline. Last seen 5 years 11 weeks ago. Offline
Joined: 19 Dec 2017
Posts: 39
Groups: None

learn everything about the EXTENSION OF TIME

Khuong Do
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 22 Feb 2010
Posts: 119
Groups: None

Hi,

I write an article regarding How to perform Time Impact Analysis / Window Analysis in Primavera P6.

If you're interested, kindly read it here https://doduykhuong.com/2016/09/10/how-to-perform-time-impact-analysis-window-analysis-in-primavera-p6/

Patrick Weaver
User offline. Last seen 3 days 5 hours ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

For a basic summry of the various options see: http://www.mosaicprojects.com.au/Resources_Papers_035.html

The main paper is Assessing Delay and Disruption - Tribunals Beware 

AACEi have a very detaild practice note on this topic.

Elsayed Ibrahim
User offline. Last seen 7 years 38 weeks ago. Offline
Joined: 11 Mar 2012
Posts: 3
Groups: None

there is no any difference just only primary method and derivative method

please see the following table

Time analysis methods as per the following table

General Approach

Primary Method

Secondary Derivative Methods

Additive

1.Impacted As-Planned

 

 

·      Chronological Addition of Delays (one at a time)

·      Gross addition (all delays at once)

2.Time Impact Analysis

·       Chronological Events analysis

·      Windows analysis

·      Contemporaneous  impact analysis

Subtractive

Collapsed As-Built

·     Chronological insertion of delays (one at a time)

·     Gross Insertion (all delays at once)

·     Windows analysis (delays in each windows)

Analytical

As-Planned vs As-built

·    Total time assessment

·    As planned vs As-Built windows analysis

·    Contemporaneous windows analysis

·    Month to month update

Mike Testro
User offline. Last seen 30 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Barry

I am not quite sure what you are asking.

Completed work to the left of the data date has no float because it has finished.

Uncompleted work to the right may have its float affected by early or late completion of work to the left.

Since a typical delay analysis focuses on zero float tasks it is only when the available float is remove by late completion of predecessors that they form part of a delay analysis.

Best regards

Mike Testro

Barry Fullarton
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 27 Aug 2008
Posts: 101
Groups: None

Hi Mike

 

Have been reading with interest on GPM and Forensic Total Float , interesting on what it says and has a good basis on CPM to the left and right of the data dates

 

What is your perspective on this ?

Mike Testro
User offline. Last seen 30 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Kristopher

Time Impact analysis (UK Definition) is a one off retrospective delay analysis excercise.

Windows Analysis is the same thing repeated many times in different time slots - even if you know what happened in the following months you have to pretend that you don't know. That makes it useless for forensic work.

For work in progress the Impacted as Planned method (UK Definition) goes on as the work progresses - that makes it a Windows analysis.

Best regards

Mike Testro