Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Creating Target plan

5 replies [Last post]
Forum Guest
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I want to make a target plan. What shall I do?

Replies

Bernard Ertl
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Yes, it appears to be a duplicate thread. I’m locking this one then. We do not need two threads for one subject.

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
MK TSE
User offline. Last seen 4 years 10 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Hope they are related.

http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=3875

According to what pasted, I assume the software is P3.
Bernard Ertl
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Folks, the original question did not specify what software was being used. This forum is for general discussions and assumptions should be checked carefully.

Perhaps the original question was answered already?

http://www.planningplanet.com/forum/forum_post.asp?Cat=1&Top=2936

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Luca Basile
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
As suggested before, copy the schedule.
Open the schedule you updtae. In the load form, go on "Overview", select the Target, and then You can put multiple target.
Let say first the baseline, then last update period.

When You open the program, in the bars management, must add the target bars (target 1 early start and finish) and in a different level(POS), fo example level 2.

The same for how amny target You added or You want to show.

Of course You can compare late dates on so on.
Zq qz
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
1st Method. >>> Go to TOOLS >> PROJECT UTILITIES >>> TARGET >> CREATE BY TYPING NAME OF PROJECT YOU WANT ....

2ND mETHOD : COPY YOUR ORIG PROJECT. THEN USE THIS AS TARGET.

You can also go to help for more info........