Creating Target plan

5 replies [Last post]
Pelita De Ramos
User offline. Last seen 20 years 4 weeks ago. Offline
Joined: 26 Jul 2003
Posts: 3
Groups: None
Based from what I’ve red in creating target plan (from P3 manuals). Pls. check the ff procedures if I’m wrong.

1. Prepare schedule with resources.
2. Open tools menu -> project utilities -> target
3. Enter 4 chars. name.
4. Click OK.

But nothing happens, any suggestions will be highly appreciated. thanks. :)

Replies

wilfred datinguinoo
User offline. Last seen 18 years 28 weeks ago. Offline
Joined: 14 Feb 2004
Posts: 20
I’ved run a check now on the Project Overview and its ok
and i check also format bar/modify then i didn’t noticed
that my start point is not in Target early start.

Thanks for your help.

Regards,
wilfred
MK TSE
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
I can’t get it. Target bar always parallel to the currect bar except they are placed in same position. Please check the following: -
- Have target been assigned in Project overview
- What option been selected in bar format
wilfred datinguinoo
User offline. Last seen 18 years 28 weeks ago. Offline
Joined: 14 Feb 2004
Posts: 20
Hi Guys,

In relation to Pelita’s question, I’ved done copying the project and make it as a target. But when i tried to show the target bar it appears to be not parallel with the current and it shows a long bar. Let say the project starts Jan 2004 and my activity starts May 2004 and end june the target bar shows Jan - June.

Need Help

Thanks,

wilfred
MK TSE
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Pelita,
Your method is to assign an Existing project as tartget and/or update the assigned target project by current open project. It is not for creating a project for target from current.

Use Moises’s method, you now have a copy. Then you part is the OK for assign. Or by File - Open - select the current project - click Overview button at bottom left, goto to page Targets, select a project for target assignment.
Zq qz
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Hello Kabayan,
You can also this procedure. Go to the ff Menu

TOOLS>>>>PROJECT UTILITIES >>> COPY ( read in the manual how to copy ...)be sure that copy file and orig file on same folder, then you can use this as your Target.