Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Progress curve - Early Vs Late and somewhere in between

2 replies [Last post]
Masood Mehman-Doost
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 12 Oct 2011
Posts: 9
Groups: None

I like to see the usage of different progress curves other than early curves, and when used, what kind of irrational was used and who agreed with it, meaning agreement between the PCMs or the PMs.  If the subject was already discussed, let me know where to go to see it.  Thanks.    

Replies

Peter Holroyd
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 6 Jun 2005
Posts: 162

used all types - ES=0%, ES=50%, ES=67%, ES=100%=LS. seems to be at the PM's whim but earliest and latest seem wrong (never achieve ES and LS gives you no time to correct). trouble with AACE RP's is (unless your a member) they cost $60.

 BUT

make sure that the planned v earned v actual data is consistent (no actual for unbudgetted work, no earned for actuals etc)

that you highlight the function your are measuring e.g. budget, commitment, manhours, quantities, benefit etc

other than ES and LS you don't have a schedule to support the indices so further detailed analysis is not possible

ALSO

say which baseline you are using b0 - original, b1 updated etc. Nothing worse that having to report negative percentage progress cause you have accepted scope changes that increase contract value

ADD

when the indices was produced (as a superscript) e.g. P6 of 28, or M5 of 35 - helps in trending

which planned curve was used (as a subscript) e.g. ES=50%

                                                                 P6 of 36

so SPI = 0.8 becomes  SPI (budget, b0) = 0.8 

                                                                 ES=50%

I have written a paper with full details if you are interested further

Peter

 

Masood Mehman-Doost
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 12 Oct 2011
Posts: 9
Groups: None

Thanks Renzo.  I'll check them out. I'm A AACE member actually, and planned to go there as well, but thought to see if any member here practicxally using it!  We are brainstorming using curves other than the early curve at work.  I have used a 50% curve before at different places.  Trying to find out how widespread this is and justify to use.  We are a Petrochemical Company exercising small expansion, revamp, and debottleneck projects ranging from 25 to $400M, having EPCM companies do them for us. Thanks again.     

Renzo Constenla B...
User offline. Last seen 9 weeks 2 days ago. Offline
Joined: 23 Mar 2011
Posts: 21

Dear Masood:

there is a extense literature about to S-curves that you can easily find in the web.

I recommend you -among other documents and papers- the Recommended Practice 55R-09 of the AACE (PMI is another good source).

 

regards