Generating an Early, Late, & Planned Curve in P6

In P3, users could produce an Early, Late, & Planned Curve.  P6 doesn't do this. 

I am able to produce an Early & Late Resource curve by copy/pasting the data from the resource assignments view into an excel spreadsheet, but I cannot produce a planned curve.

I am curious to know what others are doing to generate a planned curve from P6 without simply taking the average of the early & late units. 

R
Raymund de Laza 👤 Member for 16 years 6 months

Melissa,

The early dates of your Baseline or Initial Schedule represents the Planned.
Use the Baseline to generate the required curve.

M
mohd mofaz 👤 Member for 14 years 11 months

Go to resource graph on the task bar in P6. Then right click on the graph to customize according to what you want.

Forum Sponsor

Top Posters

Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts