Problem when shifting the data date in P6 using Update Progress option

No replies
Raul Santos
User offline. Last seen 5 years 43 weeks ago. Offline
Joined: 29 Oct 2009
Posts: 44
Groups: None

The problem that I am getting is that instead of getting the desired results, my activities are getting screwed up when I do this operation (Tools->Update Progress->Apply).

The desired results are those that are indicated in the Help option for this topic, explained here:

Apply: Click to update each applicable activity. For each activity in the update, the Project Management module sets dates to actual if they fall before the new data date, calculates actual duration and units, and calculates remaining durations for activities that are not finished as of the data date.

Note

You must have the Apply Actuals project security privilege to update progress.

It llooks like I don't have this security privilege, how can I find out about that? Would that be the only reason as to why my activities get screwed up when I shift the data date using Tools->Update Progress->Apply?