Performance % Complete

3 replies [Last post]
Emma Lang
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 9 Aug 2016
Posts: 45
Groups: None

I've created a new project in P6 Version 20, and the performance % complete doesn't match the activity % complete. 

Is there a setting I need to change to make sure these two columns show the same data?

 

thanks

Replies

Rodel Marasigan
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

The activity performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

You can set the performance percent complete under WBS module. See below:

Performance-percent-Complete

Zoltan Palffy
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Tools

Admin Preferences

Earned Value Tab

Make sure that the Technique for computing performance percent complete is set to

Activity % Complete

and that Earned value calculation is set to Budgeted Values with current date is at the bottom of this same tab.

Also at the Project levele under Setings make sure that Baseline for earned value calculatons is  set to Project Baseline

david kelly
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

It is at the WBS level, the Earned Value tab.