Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Dates Don't Match Activity Dates

3 replies [Last post]
Alex Garcia
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

We keep having the issue of resource dates randomly changing.  Not only do they not match the activity dates, after we fix them, a differnt batch crops up. 

I realize there is the check box to "drive activity dates" for a given resource assignment.  However, I don't want the resource dates to drive the activity dates, and unchecking the box isn't having the "opposite" effect of the activity dates driving the resource dates.  Example.....one of my team members statused an activity with the start date of 9/27/21.  However, the resource dates show an actual start of November 1.  November 1 also happens to be the planned start.  This is very aggravating as it's causing forecasting isssues, as well as integration issues with Cobra. 

 

Thoughts?

Replies

Alex Garcia
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

Great information....thank you!

David Kelly
User offline. Last seen 2 years 36 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Never, ever, untick 'drive activity dates'

BUt now that you have used it, you need to get rid on the lag and duration at the resource assignment level.

simplest way to do this is to display the column in the resource assignment window, and fill down.

Did I mention never unticking 'drive activity dates@?

Rodel Marasigan
User offline. Last seen 13 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Alex,

If you removed the tick the "drive activity dates" options on resource assignment you are de-linking the relationship of Activity and Resource which causing resources date and activity date different. If your activity type is "Task dependent", resource assigned will use task calendar and ignore the resource calendar. If the activity type is "Resource dependent" then the resource is using resource calendar. If you wanted Activity and resource assigned have the same date, make sure that "drive activity dates" option is ticked or if you don't want a non-driving resouces then you have to remove/ un-ticked all "drive activity dates".

Please note P6 always applies the following rules:

- When scheduling on the forward pass, if the activity has any driving resource assignments, P6 Professional calculates the early start date of the activity as the earliest Early Start date of all driving resource assignments. Once the Early Start of the activity is calculated from the driving assignments and relationships, all nondriving resources are scheduled on or after this date using its assignment duration. The Early Finish dates of the nondriving assignments can fall earlier or later than the Early Finish of the activity.

- When scheduling on the backward pass, the Late Start date of the activity and all nondriving resources are calculated as the earliest Late Start date of all driving resource assignments. Once the Late Start date of the activity is calculated from the driving assignments and relationships, all nondriving resources are scheduled on or after this date using its assignment duration. This means the Late Finish date of the nondriving assignments can fall later than the Late Finish date of the activity to which they are assigned.

 - The finish dates of the nondriving resource assignments can fall later than the latest calculated Early Finish date of the project, which is driven by the activity dates.

- If no driving resources exist on the activity, the activity dates are used as the calculated dates for the nondriving resources.